Skip to content
In forceClimate and energy

Cer­ti­fi­ca­tion of transmission system operators controlled from countries outside the EU

Official title (in Danish): Bekendtgørelse om certificering af trans­mis­sionssel­skaber, som kontrolleres af en eller flere fysiske eller juridiske personer fra et eller flere lande udenfor EU

Executive order · BEK nr. 631 af 30.06.2026 · Klima-, Energi- og For­syn­ings­min­is­ter­iet

In short

Reading time: 1 min
  • What changes:
    • The Danish Supply Authority (Forsyningstilsynet) now decides on certification instead of the Danish Energy Regulatory Authority (Energitilsynet).
    • The rules now cover methane gas transmission system operators (instead of natural gas transmission system operators) and hydrogen transmission system operators (new).
    • Electricity transmission undertakings are still covered.
    • The minister's assessment now also covers essential security interests.
    • For methane gas and hydrogen transmission system operators, the deadline for a draft decision is 100 working days, and the final decision must be issued no later than 50 working days after the expiry of the Commission's deadline for handling the case. (For electricity companies, the 4-month deadlines still apply.)
  • Who: The rules apply to electricity transmission undertakings, methane gas transmission system operators and hydrogen transmission system operators that are controlled from countries outside the EU.
  • When: The executive order entered into force on 5 August 2026.

Written by AI from verbatim quotes from the source and checked by code and AI. Dates, tables and the fact box are calculated by fixed rules. Unofficial translation. Always read the original.

Sources and original

Read the official text (in Danish) →

Source: Retsinformation.dk

Translated from Danish · The Danish version and the original source apply.

Timeline

How to read the timeline

  • Filled dot: this has happened. The date and the source are shown below the point.
  • Empty dot: an upcoming step. The date may be known or not known yet.
  • Square: the case ended here, e.g. because the bill was rejected or withdrawn.
  • "The date is in the source, but entry into force has not been confirmed yet" (or just "not confirmed yet") means the date has passed, but the source does not yet show that the law or rule has entered into force. We only change the status when the source confirms it.
  1. Issued · 30 June 2026
  2. Published in the Danish Law Gazette (Lovtidende) · 3 July 2026
  3. In force · 5 August 2026