In forceTransport and rural areas
Rules for an energy park at Farris
Official title (in Danish): Bekendtgørelse om en energipark ved Farris i Kolding Kommune
In short
Reading time: 1 min- What it sets out:
- The executive order designates an area at Farris in Kolding Municipality as an energy park.
- The purpose is to promote the installation of wind turbines and solar power plants.
- When planning solar power plants, there must be at least 150 metres to villages, summer house areas and allotment areas.
- The distance to neighbouring houses depends on how many sides of the house will have solar panels.
- Who: The rules apply to the planning of solar power plants for the realisation of the energy park at Farris. They particularly affect the municipality that does the planning, as well as neighbours of the solar power plants.
- When: The executive order entered into force on 11 July 2026.
Written by AI from verbatim quotes from the source and checked by code and AI. Dates, tables and the fact box are calculated by fixed rules. Unofficial translation. Always read the original.
Sources and original
Read the official text (in Danish) →
Source: Retsinformation.dk
Translated from Danish · The Danish version and the original source apply.
Timeline
How to read the timeline
- Filled dot: this has happened. The date and the source are shown below the point.
- Empty dot: an upcoming step. The date may be known or not known yet.
- Square: the case ended here, e.g. because the bill was rejected or withdrawn.
- "The date is in the source, but entry into force has not been confirmed yet" (or just "not confirmed yet") means the date has passed, but the source does not yet show that the law or rule has entered into force. We only change the status when the source confirms it.
- Issued · 6 July 2026
- Published in the Danish Law Gazette (Lovtidende) · 10 July 2026
- In force · 11 July 2026