Energy park at Stae in Aalborg Municipality

Official title (in Danish): Bekendtgørelse om en energipark ved Stae i Aalborg Kommune

Executive order · BEK nr. 652 af 06.07.2026 · By-, Land- og Trans­port­min­is­ter­iet

In short

Reading time: 1 min
  • What it sets out: An area in Aalborg Municipality has been designated as an energy park for the promotion of wind turbines and solar cells.
  • Who: The rules apply to the designation of the area as an energy park and to the planning of solar cell installations for the energy park. As a general rule, solar cell installations must be 150, 300 or 750 metres away from housing, depending on how many sides of the house the installation is located on, and at least 150 metres from villages, summer house areas and allotment gardens.
  • When: The executive order entered into force on 11 July 2026.

Written by AI from verbatim quotes from the source and checked by code and AI. Dates, tables and the fact box are calculated by fixed rules. Unofficial translation. Always read the original.

Sources and original

Read the official text (in Danish) →

Source: Retsinformation.dk

Translated from Danish · The Danish version and the original source apply.

Timeline

How to read the timeline

  • Filled dot: this has happened. The date and the source are shown below the point.
  • Empty dot: an upcoming step. The date may be known or not known yet.
  • Square: the case ended here, e.g. because the bill was rejected or withdrawn.
  • "The date is in the source, but entry into force has not been confirmed yet" (or just "not confirmed yet") means the date has passed, but the source does not yet show that the law or rule has entered into force. We only change the status when the source confirms it.
  1. Issued · 6 July 2026
  2. Published in the Danish Law Gazette (Lovtidende) · 10 July 2026
  3. In force · 11 July 2026