Did not become law: Repealed before entering into forceClimate and energy
The Pipeline and Cable Owner Register
Official title (in Danish): Bekendtgørelse om Ledningsejerregistret
In short
Reading time: 1 min- What changes:
- Tasks that used to sit with the Pipeline and Cable Owner Register are now handled by the Danish Climate Data Agency.
- This includes, for example, limits on excavation enquiries and rules for electronic identification.
- An announcement about excavation work must now include, among other things, the location, the expected start date and a contact point.
- A pipeline or cable owner must respond to reasonable requests for information about its passive physical infrastructure within 10 working days.
- In duly justified cases, the deadline can be extended once by five working days.
- Who: The rules apply to pipeline and cable owners and excavation operators.
- When: The executive order was repealed before it entered into force.
Written by AI from verbatim quotes from the source and checked by code and AI. Dates, tables and the fact box are calculated by fixed rules. Unofficial translation. Always read the original.
Sources and original
Read the official text (in Danish) →
Source: Retsinformation.dk
Translated from Danish · The Danish version and the original source apply.
Timeline
How to read the timeline
- Filled dot: this has happened. The date and the source are shown below the point.
- Empty dot: an upcoming step. The date may be known or not known yet.
- Square: the case ended here, e.g. because the bill was rejected or withdrawn.
- "The date is in the source, but entry into force has not been confirmed yet" (or just "not confirmed yet") means the date has passed, but the source does not yet show that the law or rule has entered into force. We only change the status when the source confirms it.
- Issued · 20 August 2026
- Published in the Danish Law Gazette (Lovtidende) · 25 August 2026
- Ophævet, før den trådte i kraft · 1 September 2026The case ended here.