Skip to content
In forceClimate and energy

New rules for prioritising capacity and refusals when the electricity grid has capacity limits

Official title (in Danish): Bekendtgørelse om prioritering af kapacitet og afslag ved ka­pa­citets­be­græn­s­ninger i det kollektive elforsyningsnet

Executive order · BEK nr. 892 af 09.10.2026 · Klima-, Energi- og For­syn­ings­min­is­ter­iet

In short

Reading time: 1 min
  • What it sets out:
    • The executive order sets out how collective electricity supply companies prioritise capacity in the electricity grid, and when they must refuse connection when there are capacity limits.
    • Capacity is divided into four categories, where category 1 comes first.
  • When: The executive order entered into force on 19 October 2026.

Written by AI from verbatim quotes from the source and checked by code and AI. Dates, tables and the fact box are calculated by fixed rules. Unofficial translation. Always read the original.

Sources and original

Read the official text (in Danish) →

Source: Retsinformation.dk

Translated from Danish · The Danish version and the original source apply.

Timeline

How to read the timeline

  • Filled dot: this has happened. The date and the source are shown below the point.
  • Empty dot: an upcoming step. The date may be known or not known yet.
  • Square: the case ended here, e.g. because the bill was rejected or withdrawn.
  • "The date is in the source, but entry into force has not been confirmed yet" (or just "not confirmed yet") means the date has passed, but the source does not yet show that the law or rule has entered into force. We only change the status when the source confirms it.
  1. Issued · 9 October 2026
  2. Published in the Danish Law Gazette (Lovtidende) · 15 October 2026
  3. In force · 19 October 2026