Energinet assigns connection points in the transmission grid

Official title (in Danish): Bekendtgørelse om systemansvarlig virksomhed og anvendelse af el­trans­mis­sion­snettet m.v

Executive order · BEK nr. 895 af 09.10.2026 · Klima-, Energi- og For­syn­ings­min­is­ter­iet

In short

Reading time: 1 min
  • What changes: Energinet assigns a connection point in the transmission grid for electricity production, electricity consumption and energy storage facilities, and to ensure reliable and secure operation of the collective electricity supply grid and electricity supply security, it may decide whether facilities are connected as one or more facilities, and the decision can be appealed to the Danish Utility Regulator (Forsyningstilsynet) if the complaint is submitted no later than 4 weeks after the decision was communicated to the person concerned.
  • When: The executive order entered into force on 19 October 2026.

Written by AI from verbatim quotes from the source and checked by code and AI. Dates, tables and the fact box are calculated by fixed rules. Unofficial translation. Always read the original.

Sources and original

Read the official text (in Danish) →

Source: Retsinformation.dk

Translated from Danish · The Danish version and the original source apply.

Timeline

How to read the timeline

  • Filled dot: this has happened. The date and the source are shown below the point.
  • Empty dot: an upcoming step. The date may be known or not known yet.
  • Square: the case ended here, e.g. because the bill was rejected or withdrawn.
  • "The date is in the source, but entry into force has not been confirmed yet" (or just "not confirmed yet") means the date has passed, but the source does not yet show that the law or rule has entered into force. We only change the status when the source confirms it.
  1. Issued · 9 October 2026
  2. Published in the Danish Law Gazette (Lovtidende) · 16 October 2026
  3. In force · 19 October 2026